Rehabilitation of Nyerere road 0.706km, Nyerere Avenue 0.42km and Kigongi road 0.80km Kabale Municipality
Abstract
The Government of Uganda, through the Ministry of Lands, Housing and Urban
Development (MoLHUD) using funding from the World Bank, formulated a program,
Uganda Support to Municipal Infrastructure Development (USMID), to improve urban
infrastructure conditions in fourteen (14) municipalities of Arua, Entebbe, Gulu, Hoima,
Jinja, Kabale, Masaka, Tororo, Soroti, Mbale, Lira, Moroto, Fort Portal and Mbarara. The
program is intended to be implemented over a period of 5 years with a projected budget of
USD 150million.
Kabale Municipal council prioritized 3 roads within the municipality under phase one of the
project namely Nyerere road 0.706KM, Nyerere Avenue 0.42KM and Kigongi road
0.80KM.
Kabale municipal council (KMC, the employer) and stone construction limited (SCL the
contractor) entered in to contract agreement (the contract) for the construction works of
Rehabilitation of Nyerere road 0.706KM, Nyerere Avenue 0.42KM and Kigongi road
0.80KM.
The agreed contract price quoted in the contract was UGX 13,018,632,421 (Ugandan
shillings thirteen billion eighteen million six hundred thirty two thousand four hundred
one)
Through a letter Ref: CR/2019/1 dated 29 April 2016, the employer set the commencement
date as April 29 2016 and possession of the site was given to the contractor on the same date
Kagga and partners was appointed as project manager of the project by the employer and the
project manager issued a notice to commence works vide a letter ref: KG/02/001/PM dated
2nd May 2016
This report detail all the account of how the project was run from signing the contract
through to completion and final accounts
Chapter one give details of the project brief, the location of the project, the project area its
people and the climatic conditions.
Chapter two details the project context, the stake holder analysis, the SWOT (Strength,
Weakness Opportunities and Threats) analysis and how these contributed to project success
and lessons learnedxiii
Chapter three gives details of how the three main parties in the project namely the employer,
contractor and the consultant were organized and the relationship between the different
structures and the flow of command chain and communication within these structures.
Chapter four details the implementation of the project. The author gives the account of the
execution of project tusks of mobilization, setting up laboratories, relocation of services,
earth works, Sub-base construction, base construction, wearing course construction, drainage
works and auxiliary works.
Chapter five gives detailed account of the project management from cost management of the
project, time management, quality management, risk planning and management
Chapter six details the environmental, health and safety management of the project
Chapter seven details key decisions made, challenges face and how the challenges where
addressed
Chapter eight give the conclusions, lessons learned and recommendations.