School of Built Environment (SBE) Collections: Recent submissions
Now showing items 161-180 of 347
-
Design and construction supervision of Ayivu solar powered water supply system in Bidibidi Settlement, Yumbe District
(Makerere University, 2022)This project Report is submitted to Makerere University in partial fulfilment of the requirements for Award a Post-Graduate Diploma in Construction and Project Management of Makerere University. The report covers the Design ... -
Project management and implementation strategy for the periodic maintenance of Kibuye – Entebbe Road (22km).
(Makerere University, 2022-05-04)This report was drafted as part of the requirements for completion of a Post Graduate Diploma in Construction Project Management at the College of Engineering, Design, Art and Technology, Makerere University. It contains ... -
Construction of an office building for Insurance Regulatory Authority
(Kampala, Makerere University, 2020-05)This project report contains details about the construction of the Insurance Regulatory Authority (IRA) Office Building, located at Plot 10 Lumumba Road on Nakasero Hill, in the Central Division of Kampala, as of May ... -
The expansion of Uganda Technical College Kichwamba, Phase II
(Makerere University, 2021)The on-site work was undertaken for the period of 36 months, from 24th September 2015 to 30th September 2018 at the project for The Expansion of Uganda Technical College, Kichwamba with Pearl Engineering Company Limited ... -
Education infrastructure enhancement project in Bidi Bidi refugee settlement Yumbe district.
(Makerere University, 2022-05-04)By the end of March 2017 Uganda had become host to 1,199,051 refuges, with over 68% from South Sudan. The South Sudanese refugee population in Uganda was 880,211 by the 15th of April 2017, mostly in the West Nile district, ... -
The expansion of Uganda technical college Kichwamba, phase 11.
(Makerere University, 2021-10-19)The on-site work was undertaken for the period of 36 months, from 24th September 2015 to 30th September 2018 at the project for The Expansion of Uganda Technical College, Kichwamba with Pearl Engineering Company Limited ... -
The supervision and execution of the periodic maintenance of selected unpaved national roads in 23 UNRA stations lot 3: Gulu station: Gulu – Opit – Odek bridge road (63.1km)
(Makerere University, 2022-04-07)This project report contains details of the supervision and execution of the Periodic Maintenance of Selected Unpaved National Roads for 23 UNRA Stations (Lot 3: Gulu Station): Gulu – Opit – Odek Bridge Road (63.1 Km) ... -
Project report for construction of Mparo seed secondary school in Kyenjojo district.
(Makerere University, 2022-02-18)This project report contains details of construction of Mparo Seed Secondary School in Kyembogo Sub County, Kyenjojo District. Kyembogo Sub County is in the north of Kyenjojo Distict and boarders Kagadi district. Mparo ... -
Technical project report for civil works of upgrading Kaguta road 1.50km from gravel to bituminous standard in Kyenjojo Town Concil Kyenjojo District.
(Makerere University, 2022-02-16)This project report contains details about the civil works for upgrading of Kaguta road from gravel to bitumen standard in Kyenjojo Town Council, Kyenjojo District as of December 2021. The report focuses on construction ... -
Constructing a commercial development consisting of workshop, training block, office block, warehouse and support facilities (powerhouse, car wash and spray room, guard house)
(Makerere University, 2022-04-20)The Project Report highlights a skimpy overview of the procurement process of the contractor and the scope of works. The scope of works comprised of the Construction of a 3 storey Office building of approximate area of ... -
Construction of multi-purpose storey block (classrooms, laboratories, libraries, and toilet facilities) at Musima, Jinja District
(Makerere University, 2022-04-20)While Construction projects regularly involve a variety of skills that originate from the diversity professionals, specialists and suppliers, Successful implementation of a construction project can only be achieved if ... -
Impact of use of force account mechanism for maintenance of roads in Nakasongola Town Council.
(Makerere University, 2022-03-28)Overtime road works in Local Governments were contracted out to service providers until June 2012 when agencies were allowed to use own equipment and personnel under Force Account arrangement. This report presents positive ... -
Upgrading 0.2km of Community Lane from earth road surface to bituminous surface in Kakooge Town Council.
(Makerere University, 2021-10-22)This report describes one of the projects that were implemented in Kakooge Town Council in which the author was the supervisor of the executed works. It is intended for presentation to Makerere University in partial ... -
Design review and construction supervision of Kakooge Town water supply system in Nakasongola District.
(Makerere University, 2022-05-09)This report is written in partial fulfillment of the requirements leading to the award of a Master of Science in Construction Management of Makerere University. The main aim of the project was to provide clean and safe ... -
Exploring the use of PPGIS for mapping the distribution of Vitellaria Paradoxa (SHEA TREE).
(Makerere University, 2022)Vitalleria paradoxa is a tree of high economic and cultural value to the local communities of West Nile, Northern Uganda and Teso region where it is endemic in Uganda. The tree is however listed as vulnerable by the ... -
Upgrading of Buwali mixed use neighbourhood in Kyengera town council, Wakiso district.
(Makerere University, 2022-05)This report is mainly about the upgrading of Buwali Mixed Use Neighbourhood in Kyengera Town Council Wakiso District, it looks at the historical back ground of the area and how the area came into existence. The ... -
Assessing the impact of spatial planning on the spread of COVID-19 in Kampala City.
(Makerere University, 2022-05-09)Spatial Planning has long been recognized as a vital factor in the dynamics of pandemics and has previously played a major role in the long-term eradication of health crises. In the context of COVID-19, it has not been ... -
Construction of residential apartments on plot 4909 and 4910, block 178 Gayaza Manyangwa, Wakiso District
(Makerere University, 2022-02-14)The report gives details of the Construction and Project Management Practices that took place during the execution of the Residential apartments at Manyangwa-Gayaza, Kyadondo County Wakiso District. It is made up of four ... -
CONSTRUCTION OF THE VISITORS CENTRE AT THE ISIMBA HYDROPOWER PLANT
(2022-02-07)1.1 Introduction Isimba hydropower Plant Visitors Center has been developed under a Design and build contract with China International Water and Electricity Corporation as one of the supporting facilities to be used by ... -
Construction of Boro Solar powered gravity flow piped water supply system in Pakwach District.
(Makerere University, 2021-12-29)The construction of Boro solar powered gravity flow piped water supply system is aimed at supplying clean, safe portable water to Boro community. Some expected outcomes of the water supply project are reduced prevalence ...