The effect of changing construction drawings on the project : a case study of the construction of additional building for FAO office in UNMISS Compound, UN House, JUBA, South Sudan.
Abstract
This project explores the how change of construction drawings in the construction phase
influences the project duration and cost, using the construction of Food and Agriculture
Organization additional office in Juba South Sudan.
The project, contracted to Emaha General Construction and Trading Company, experienced
significant delays and cost overruns due to changes in construction drawings. The total cost of
the project was 26% higher than the original estimate, primarily due to additional work not
included in the original drawings. The project duration extended from the planned 176 days to
429 days, with changes in construction drawings contributing to 90.11% of this delay. Despite
these challenges, some tasks were completed on time or ahead of schedule. This report provides
a detailed analysis of the project schedule, cost, and the impact of changes in construction
drawings on the project's timeline and budget.