Design and implementation of an energy metering environment protection system
Abstract
This dissertation describes the research study done to design and implement an energy metering
environment protection system applicable to three-phase metering systems. The metering
environment is the energy meter, its enclosure, and the cables that bring and take out power from
this energy meter. Over the past years, Umeme Limited has tried to reduce energy losses from
26.1% recorded in 2012 to 18% in 2021 but this is still high, and the problem of high energy losses
still exists to date, a big percentage of these losses being commercial losses. Taking an example
of year 2021, Umeme planned to have reduced the losses to 14% from the 17.5% in June 2021 but
in June 2022, the losses instead had increased to 18% instead of reducing.
Electricity is stolen in different approaches within and outside the energy meter including direct
hooking from the utility powerline. Umeme has tried to reduce electricity theft by installing
automated meter readers, smart meters, and aerial bundled conductors but gaps in these solutions
still exist. High energy losses affect the final electricity tariff rate that the end user pays for using
electricity. One of the major gaps that exists in the existing solutions is the inability to capture
some bypasses and tampered/ faulty energy meters.
This thesis describes an anti-theft device that was researched about and developed based on the
different electricity theft approaches often used to steal electricity. It would be installed between
the energy meter and customer circuit breaker to monitor consumption and detect electricity theft
with logic of behavior of three-phase systems instantaneous values under normal and bypassed
conditions introduced by an external circuit. Also, three-phase star configured circuits neutral
currents differ when a system is by-passed from the normal metered circuit.
This thesis further describes the functionality tests that were done on this developed device through
simulations in NI multisim and field tests. A prototype was developed and installed in the field
environment to test its functionality. A cost benefit analysis showed a positive net present value
and a two-year payback period which indicated that the project would be a viable one to take up.