Technical project report for the construction of the proposed Kireka Adventist Hospital.
Abstract
This project report contains details about the construction of the Proposed Kireka Adventist
Hospital in Wakiso District as of January 2021. The report focuses on construction project
management and contract administration, but also details the activities carried out during the
implementation of the project. Under Chapter One is discussed the background of the project,
its objectives, scope and other project details like the contract sum, duration and the different
stakeholders. This chapter also expressly states the author’s involvement on the project as an
intern contractor’s project manager.
Chapter Two covers the project execution including the acquisition of works, construction
activities and processes, project management and contract administration aspects of the project.
The different tools and techniques used in the actual construction that took place on site are
discussed in this chapter, right from substructure, through finishes. The project management
techniques employed to manage time, cost and quality are also discussed in detail.
The challenges encountered during project execution are discussed in Chapter Three of this
report. Some of the challenges were at individual level, while others were at company level,
project level and activity level. The solutions proposed to address these challenges are also
discussed in this chapter.
Chapter Four details the conclusions drawn by the author about execution of the Proposed
Kireka Adventist Hospital project based on the experiences drawn during his participation in
this project. Additionally, the author makes recommendations on how this can be successfully
implemented, going forward, basing on the lessons learnt during the internship.