Technical project report for civil works of upgrading Kaguta road 1.50km from gravel to bituminous standard in Kyenjojo Town Concil Kyenjojo District.
Abstract
This project report contains details about the civil works for upgrading of Kaguta road from
gravel to bitumen standard in Kyenjojo Town Council, Kyenjojo District as of December 2021.
The report focuses on construction project management and contract administration, but also
details the activities carried out during the implementation of the project. Under Chapter One is
discussed the background of the project, its objectives, scope and other project details like the
contract sum, duration and the different stakeholders. This chapter also expressly states the
author’s involvement on the project as an intern contractor’s site manager. Chapter Two covers
the project execution including the acquisition of works, construction activities and processes,
project management and contract administration aspects of the project. The different tools,
equipment and techniques used in the actual construction that took place on the road are
discussed in this chapter, right from setting out, through tarmacking. The project management
techniques employed to manage time, cost and quality are also discussed in detail. The
challenges encountered during project execution are discussed in Chapter Three of this report.
Some of the challenges were at individual level, while others were at company level, project
level and activity level. The solutions proposed to address these challenges are also discussed in
this chapter. Chapter Four details the conclusions drawn by the author about execution of the
Kaguta Road project based on the experiences drawn during his participation in this project.
Furthermore, the author makes recommendations on how this can be successfully implemented,
going forward, basing on the lessons learnt during the internship.