dc.description.abstract | This report details a host of construction and project management practices that the author
participated in as the Contractor’s Assistant Project Manager and Quantity Surveyor during the
Rehabilitation and Expansion of Uganda Technical College, in Masindi District along Masindi –
Kigumba Road.
Chapter One; lays out an introduction of the project, briefly discussing the background of the
project, the scope, the funders, consultants and other stakeholders. The project was entailed with
a lecture theatre two storey, library block two storey, laboratory block two storey, CAD
laboratories two storey, Boys’ hostel block two storey, machine and welding workshops, gate
house, underground water tank and external works, constructed for UTC Kyema under the
MoESTS. It also states the author’s involvement from pre-contract stage through to completion.
Chapter Two; discusses the construction methodologies, activities and contract administration
procedures undertaken during the execution stage of the project. The different tools and techniques
used in the actual construction that took place on site are discussed in this chapter, right from
substructure, through finishes and to fittings.
Chapter Three; discusses the project management knowledge used during implementation and
administration of this contract. The different project management knowledge areas are explored in
the context of the project, with particular emphasis accorded to scope, cost, quality, time,
procurement and communication management.
Chapter Four; is a discussion of the entire project in general and conclusion. It discusses some of
the prevailing conditions in the industry world over and also in the context of the project and makes
a few recommendations on what would have been done differently to improve the successes
attained on the project.
Construction projects often involve a variety of skills that come from the diversity of professionals,
specialists and suppliers that are involved in the process from inception to close out. Successful
implementation of a construction project can only be achieved if good project management
practices and systems are put in place and allowed to work. It is important that an enabling
environment is maintained to encourage project participants to follow and use these systems. A
lapse in project control, monitoring and management systems will ultimately affect the
implementation of the project and can easily result in budget & time overruns and even affect the
quality of the work. Of course this leads to loss in value; to the client in terms of potential income,
to the contractor in penalties loss to government in terms of potential tax revenue. | en_US |