Project Field Report for the Construction Of Residential Houses on Plot 3 Block 256, Munyonyo
Abstract
This project report entails the construction methodology used and aspects of construction project
management practices exercised by the author while part of the construction team during the
construction of the 2No.residential villas on plot 3 block 256 Walugembe road Munyonyo.
It further details contract administration practices during the execution stage and the application
of project management knowledge areas during project implementation. The knowledge areas
discussed at length include scope, cost, time and quality management. The construction
methodology adopted by the contractor at every stage of the works has also been discussed at
length in this report.
The project was of a gated community estate consisting 2No.identical high-end residential villas
constructed for Mr. Frederick Mutebi Kitaka, a real estate developer who develops private closed
gated communities targeting a specific market niche.
Construction projects involve a diversity of skills that come from the diversity of professions,
specialists and suppliers that are involved in the process from inception to end. Successful
implementation of a project can only be achieved with good project management practices in
place. Failure to have proper project management monitoring and control systems can easily
result in poor relationships, disputes and cost and time overruns on a project.