Design and construction supervision of pipeline route of Kampala-Katosi Transmission Project
(2019-04)This Technical report is submitted as part of the requirements for application for admission as a Corporate Member of Uganda Institute of Professional Engineers and for registration by the Engineers Registration Board of ... -
Periodic maintenance of selected roads in Bulambuli Town Council and graveling of roads in Bunambutye Resettlement Area in Bulambuli District Local Government Project Report
(Makerere University, 2019-09)The purpose of this project report is to describe the project aspects, technical findings and aspects of construction project management practice exercised by the author or student while working alongside other participants ... -
Construction/re-construction of strategic bridges in Eastern and Central Regions (3 LOTS): LOT 1: Kabaale Bridge on Kyankwanzi-Ngoma Road
(2019-03)This technical Project report has been prepared in partial fulfillment of the requirements for the award of the master of science in construction management of the college of engineering design, art & technology of Makerere ... -
Project management and implementation of mechanized maintenance of selected unpaved national roads under framework for 3 years; Lot 24 : UNRA Moyo Station
(Makerere University, 2019-09-19)This project report contains details of the execution of the contract for mechanized maintenance of selected unpaved national roads under framework for 3 Years; Lot 24: Moyo Station (205 Km), in which the author of this ... -
Improvement of Muko-Rubuguri Nkuringo Road from Class C Gravel Road to Class III Bituminous surfaced standard design of section 000 to 41+000
(2019-09-26)Context: This project aims at designing a sound pavement structure with materials of appropriate thickness which can effectively support the axle loading applied by the prevailing traffic conditions for 1km stretch of 41km ... -
A technical project report for civil works for upgrading Mpigi Kanoni Road from gravel to bituminous standard (64KM)
(2019-04-23)This project report contains details of the Civil Works for Upgrading of Mpigi-Kanoni Road from Gravel (Unpaved) to Bituminous (Paved) Standard (64Km) from start to practical completion, in which the author of this report ... -
Construction of 22 No. public toilets in Kawempe Division (Kawempe Sanitation Improvement Project (KSIP)
(2019-08)This project report entails the construction methodology used and aspects of construction project management practice exercised by the author while part of the construction team during improvement of water supply and ... -
Proposed refurbishment of residential flats at Block 4 Ofwono Close, Plot 6, Upper Naguru East Road for East African Development Bank
(2019-08)The East African Development Bank (EADB) was established in 1967 under the treaty of the then East African Cooperation between Kenya, Tanzania, and Uganda. Following the breakup of the first East African Community (EAC) ... -
The construction of the apron at Arua Airfield (Phase 2)
(Makerere University, 2019-07)This report is about the Construction of the Apron at Arua Airfield-Phase 2 project, under which the author did participate as Project Manager on the Contractor’s team (Construction Manager). Detailed construction approach ... -
Atc warehouse mazinnine floor
(Makerere University, 2018-07)This report details the execution and project management tools and practices that the author took part as the project coordinator representing the client (ATC) and ensuring all the interests of the client are met during ... -
Feasibility study, detailed design & construction supervision of an alternative water intake for Rukungiri water supply
(2016)The Government of Uganda is committed to a policy for the increased provision of safe water supply and adequate sanitation to the whole population. The Rural Water and Sanitation Investment Plan and Strategy aims at provision ... -
An investigation into the productivity of block laying on building sites in Kampala
(2019-04)On many public buildings, use is made of concrete blocks. Previous research shows that the productivity of workers is a major cause of poor performance of building projects in Uganda. As such poor productivity of block ... -
Examination of the quantity surveyor’s involvement in project execution with respect to cost control. A case study of Sama Plaza on Plot 4 Kyadondo Road
(Makerere University, 2018-07)This is a three chaptered report prepared for Makerere University based on work undertaken on Sama Plaza project located on plot 4 Kyadondo Road. It’s comprised of the roles of project Quantity Surveyor (QS) during pre and ... -
Renovation of Hoima Municipal Office Block
(2018-12-12)Hoima Municipality is located in Hoima district at an important junction between major towns which offers it great potential as a commercial hub. With the proper development of the area it may contribute to the local and ... -
Assessing the extent to which value engineering is applied in the implementation of building construction projects in Uganda: Techniques and staging
(Makerere University, 2018)Value Engineering (VE) is an innovative service which involves an organized approach to the identification and elimination of un-necessary costs without loss of function, hence this study describes a Masters research based ... -
A case study of the construction of the Faculty of Business Computing at Makerere University Business School (MUBS), Nakawa Campus
(2018-12)The management of construction is an enterprise that involves many people with diverse interests, talents and backgrounds. The owner, the design professional and the Contractor comprise the primary triad of parties, but ... -
A case study of the effect and significance of project management on the construction of Vehicle Inspection Station in Mbale Municipality
(Makerere University, 2018)This project report entails the construction methodology used and aspects of construction project management practice exercised by the author while part of the construction team during construction of vehicle inspection ... -
Alwi dry corridor water supply project in Nyarwodo, Nebbi District
(Makerere University, 2018)This report is about the ALWI DRY CORRIDOR WATER SUPPLY PROJECT, in NYARWODO which was an initiative by The Ministry of Water and Environment to supply water to the people of Nebbi and ensure sanitation in the area. ... -
Rehabilitation of Lemerijoa road and the junction in Arua Municipality
(Makerere University, 2018-11-26)The Government of Uganda, through the Ministry of Lands, Housing and Urban Development (MoLHUD) using funding from the World Bank, formulated a program, Uganda Support to Municipal Infrastructure Development (USMID), to ...